03.06.2020

The first week in March was very kind to the contractors. The warm and dry weather helped firm the ground up and allowed for progress on several fronts. The foundation work for the last major pre-engineered structure – the Fieldhouse – has progressed and the contractor anticipates having all foundation work completed in the next two weeks. The roof structure for the main ice arena is almost complete and the installation of insulation and roof panels is beginning. The steel framing that will support the elevated walkway around the main ice arena seating is also being installed. More precast concrete panels are expected to arrive early next week. The lack of a prolonged cold spells over the winter has also enabled the site contractor to return to the area earlier than anticipated. Delivery of storm sewer components and their installation also began this week.