03.13.2020

Work at the MidAmerican Energy Company RecPlex was slowed this week by wet weather. The rain early in the week made it difficult for the delivery trucks and equipment to move around the site. Once things dried out, the contractor was able to start taking deliveries and placing the precast planks for the mezzanine of the main ice arena. Work continues on roof installed. The foundation work in the field house is also progressing as more of the piers along the east wall were poured.